FPSO Kwame Nkrumah: Revealing GhanaÕs Jubilee Development

 

FPSO Kwame Nkrumah: Revealing Ghana’s Jubilee Development

13 June 2013 London Evening Meeting

Chairman Bob Allwood, SUT

 

Flyer

 

Presentation

FPSO Kwame Nkrumah: Revealing Ghana’s Jubilee Development

Roger Swaine, Group Projects and Engineering Manager, Tullow Oil

The Jubilee field straddles the Deepwater Tano and West Cape Three Points licenses some 60 km offshore Ghana & 130 km southwest of the port city Takoradi. This presentation outlined the successful delivery of this “ultra fast track” project which set records for the industry and which has now been in production for more than two years. The FPSO is named the Kwame Nkrumah after the first President of Ghana and is converted from an existing Very Large Crude Carrier (VLCC) 1991 single hull tanker by MODEC in the Jurong shipyard, Singapore.

Conversion work commenced in November 2008 and FPSO arrived in Ghanaian waters June 2010. Start-up November 2010.

The subsea architecture consists of 46 km of subsea flowlines supplied by Technip, 28 km of umbilicals supplied by Aker, 19 Subsea trees, 8 manifolds and 2 riser bases supplied by FMC. 14 vessels were directly involved in installation operated from the Takoradi-Sekondi port.

 

 

 

 

 

Lessons Learnt

Lessons Learnt

5 June 2013 Aberdeen Evening Meeting

Chairman Martin Harley, BG Group

 

Report

 

Flyer

 

Presentations

Gryphon Reinstatement – Navigating Complexity, Unlocking Potential

Shona Campbell, Project Manager, Maersk Oil

The Gryphon FPSO, located 175 miles north east of Aberdeen, sustained damage in a storm on 4 February 2011 when four anchor chains broke and the vessel moved off station.  This caused considerable damage to the subsea architecture requiring the Gryphon FPSO to be towed and dry docked in Damen shipyard in Rotterdam for repairs and upgrades.  While work commenced on removing and replacing the damaged subsea equipment, Maersk Oil was designing, procuring, installing and rebuilding simultaneously.  This talk focused on lessons learned on the Subsea Reinstatement Project.

 

Brownfield Projects – Concept to Commissioning, answering the challenge

Tony Pincombe, Global Sales Manager – Brownfield Projects, GE Oil & Gas

GE Oil and Gas has now completed several Brownfield projects in the North Sea region including two major field upgrades and expansions. The scopes encompassed refurbishment, new build and technology insertion. Each challenge was driven by unique field characteristics and all incorporated varying degrees of complexity. The lessons learnt from implementing a Brownfield project from scratch have been many and this talk focused on the key lessons learnt from the initial concept phase through to the subsea commissioning.

 

Post-Macondo

Post-Macondo

22 May 2013 Newcastle Evening Meeting

Chairman Dr. Malcolm Storey, Director, Worldwide Business Portfolios Ltd

 

Report

 

Flyer

 

Overview

The Macondo Blowout caught the media attention because ‘Public opinion matters’. What this illustrates is that ‘High-Technology businesses are about much more than just the nuts and bolts’; that they are not immune from a worldview.

Yet, it is proper to ask searching quetions about the industry’s strategic awareness, and to cement the answers into practice, because the outcomes reflect the Global Oil Industry and, especially, the Subsea Sector.

This event used Post-Macondo to consider the levels of technology and the perceptions pertaining to the contemporary Oil and Gas industry.

Presentations

Design of the Marine Well Containment System

Dr. Alan Dobson, Research and Development Manager, Technip Umbilical Systems

In response to the significant risks highlighted by the Macondo incident several rapid deployment containment systems are being developed by various consortia. This presentation covered the system developed for installation in water depths up to 3000m and it will provide an overview of the system, its operation and the technology.

 

Perceptions on the British Oil and Gas Industry

Trisha O’Reilly, Communications Director, Oil and Gas UK

Oil and Gas UK’s ‘Industry Awareness’ campaign seeks to shift public perceptions that the British Oil and Gas Sector is a sunset business. It concerns efforts to improve public opinion about the contribution this Industry makes to the domestic economy because, if allowed to persist, the effects will be damaging. The initiative seeks to transform those perceptions for the better.

 

Managing Existing Fields and Assets

Managing Existing Fields and Assets

8 May 2013 Aberdeen Evening Meeting

Chairman Donald Thomson, Schlumberger

 

Report

 

Flyer

 

Overview

The North Sea is often termed a ‘mature’ offshore province. Despite this, activity levels are at an all time high. A significant amount of the present activity is related to managing existing assets to maximise return, extend field life or carry out repairs to aging infrastructure. These talks look at different aspects of managing mature offshore assets.

Presentations

SUT+ Pre-talk – Developments in Riser Integrity Monitoring

Donald Thomson, Sales Manager, Schlumberger Asset Integrity Management/Framo Engineering

SUT+ Pre–talks are targeted at developing professionals and newcomers to industry, with the aim of providing attendees with additional background subject knowledge to enhance the main SUT presentations which follow.

 

The Banff Reinstatement Project

Konstantin Nazaruk, Project Engineer, CNR International

During a storm in December 2011, the Petrojarl Banff FPSO, on contract to CNR from TeeKay, lost some of its anchors. The initial operation to stabilise the vessel, and subsequent Banff reinstatement project, to repair the damage caused to the vessel, marine systems and risers has been a fast-track project for CNR and contractors. This talk describes the incident, CNR’s response and the subsequent engineering work to reinstate the Banff FPSO and the field to production.

 

Beryl Field Redevelopment – A Methodical Approach

Paul Williams, Subsea Projects and Operations Manager, Apache North Sea

Apache have significantly expanded their presence in the North Sea both with new field developments and the purchase of older brown field assets from other operators. This talk explains the approach Apache take in evaluating how to maximise brown field assets using their recent acquisition of the Beryl field as an example.

 

BP Quad 204 Redevelopment

Andrew Train, Project Director – Offshore Activities, BP

Using the Schiehallion FPSO, BP have been operating the Schiehallion and Loyal fields west of Shetland in blocks 204 and 205 since the late 90’s. In 2008 they announced the redevelopment of the fields to allow access to additional reserves. The project is one of the biggest in the UK sector at present. The talk gave an overview of the project, the new FPSO and the planned changes to the subsea facilities.